Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation

Öz:
An excavator is a construction machine that is used at constructions which involve earthworks. Pallet orwheeled ones are preferred according to the site conditions. When choosing an excavator, the unit cost of the excavation and the duration of the excavation task play an important role. There are various factors that affectefficiency of the excavator and speed of the excavation. Factors such as bucket volume of the excavator,bucket fill rate, cycle time, swing angle, type of excavated ground, as well as environment and weather conditions influence the performance of the excavators. In this study, software which estimates duration of the excavation and number of required trucks by considering different ground and environmental conditions is developed. Moreover, the software takes hauling distances and job conditions into account. The developed software calculates statistically the effect of the uncertainties in the input parameters from the randomly generated numbers by the Monte Carlo Simulation method. The software is developed by C++ programming language. Developed software can be helpful for the state institutions and private firms to determine the risks of the time and cost estimates
Anahtar Kelime:

Belge Türü: Makale Makale Türü: Araştırma Makalesi Erişim Türü: Erişime Açık
  • [1] Šalinić, S., Bošković, G., Nikolić M. Dynamic modelling of hydraulic excavator motion using Kane's equations. Automation in Construction 44 (2014) 56–62.
  • [2] Yoon, J., Kima, J., Seo, J., Suh, S. Spatial factors affecting the loading efficiency of excavators. Automation in Construction 48 (2014) 97–106.
  • [3] Zhong, D., Hu, W., Wu, B., Li, Z., Zhang, J. Dynamic time-cost-quality tradeoff of rockfill dam construction based on real-time monitoring. Journal of Zhejiang University-Science A (Applied Physics & Engineering) 18(1) 2017 1-19.
  • [4] Cheng, T., Feng, C., Chen, Y. A hybrid mechanism for optimizing construction simulation models. Automation in Construction 14 (2005) 85–98.
  • [5] Akkoyun, Ö., Ergene, S. N. The development of new simulation based software for excavator selection. 5th International Mining Machinery Symposium, 01-02 October 2015, Eskişehir, Turkey
  • [6] Haga, M., Hiroshi, W., Fujishima, K. 2000, Digging Control System for hydraulic excavator, Mechatronics 11 (2001) 665-676.
  • [7] Nunnally, S.W. Construction Methods and Management. 6th edition, Pearson Prentice Hall, USA, 2003.
  • [8] Peurifoy, R. L., Schexnayder, C. J. Construction Planning, Equipment and Method. 6th edition, McGraw-Hill, USA, 2002.
  • [9] Yang, J., Edwards, D. J., Love, P. E. D. A computational intelligent fuzzy model approach for excavator cycle time simulation. Automation in Construction 12 (2003) 725–735
  • [10] Helton, J. C. Uncertainty and sensitivity analysis techniques for use in performance assessment for radioactive waste disposal. Reliability Engineering & System Safety 42(2–3) 1993 327-367
APA SAĞLAM B, BETTEMİR Ö (2018). Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. , 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
Chicago SAĞLAM B.,BETTEMİR Ö.H. Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. (2018): 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
MLA SAĞLAM B.,BETTEMİR Ö.H. Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. , 2018, ss.85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
AMA SAĞLAM B,BETTEMİR Ö Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. . 2018; 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
Vancouver SAĞLAM B,BETTEMİR Ö Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. . 2018; 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
IEEE SAĞLAM B,BETTEMİR Ö "Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation." , ss.85 - 94, 2018. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
ISNAD SAĞLAM, B. - BETTEMİR, Ö.H.. "Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation". (2018), 85-94. https://doi.org/2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
APA SAĞLAM B, BETTEMİR Ö (2018). Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. Journal of Construction Engineering, Management & Innovation (Online), 1(2), 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
Chicago SAĞLAM B.,BETTEMİR Ö.H. Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. Journal of Construction Engineering, Management & Innovation (Online) 1, no.2 (2018): 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
MLA SAĞLAM B.,BETTEMİR Ö.H. Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. Journal of Construction Engineering, Management & Innovation (Online), vol.1, no.2, 2018, ss.85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
AMA SAĞLAM B,BETTEMİR Ö Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. Journal of Construction Engineering, Management & Innovation (Online). 2018; 1(2): 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
Vancouver SAĞLAM B,BETTEMİR Ö Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. Journal of Construction Engineering, Management & Innovation (Online). 2018; 1(2): 85 - 94. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
IEEE SAĞLAM B,BETTEMİR Ö "Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation." Journal of Construction Engineering, Management & Innovation (Online), 1, ss.85 - 94, 2018. 2018 Volume 1 Issue 10.31462/jcemi.2018.01085094
ISNAD SAĞLAM, B. - BETTEMİR, Ö.H.. "Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation". Journal of Construction Engineering, Management & Innovation (Online) 1/2 (2018), 85-94. https://doi.org/2018 Volume 1 Issue 10.31462/jcemi.2018.01085094