TY - JOUR TI - A MATHEMATICAL MODEL FOR DYNAMIC PROJECT SCHEDULING PROBLEM AND REACTIVE SCHEDULING IMPLEMENTATION AB - In today's real-life implementations, projects are executed under uncertainty in adynamic environment. In addition to resource constraints, the baseline schedule is affecteddue to the unpredictability of the dynamic environment. Uncertainty-based dynamic eventsexperienced during project execution may change the baseline schedule partially orsubstantially and require projects' rescheduling. In this study, a mixed-integer linearprogramming model is proposed for the dynamic resource-constrained project schedulingproblem. Three dynamic situation scenarios are solved with the proposed model, includingmachine breakdown, worker sickness, and electricity power cut. Finally, generated reactiveschedules are completed later than the baseline schedule. AU - RUHLUSARAÇ, MURAT AU - Çalışkan, Filiz PY - 2020 JO - Business and Management Studies: An International Journal VL - 8 IS - 4 SN - 2148-2586 SP - 83 EP - 97 DB - TRDizin UR - http://search/yayin/detay/427371 ER -