Selection of construction machine by considering time-cost trade-offproblem

Öz:
In this study, a decision support system is developed to aid selection of earthwork equipment. Physical andeconomical attributes of five off the shelf dozers, three excavators, and seven hydraulic hammers are enteredto a spreadsheet application. Seven seismic velocity-mechanical property relationships of rock and stiff soilare derived from the literature and defined to the spreadsheet application. Mechanical properties of the soilsamples obtained from the construction site are entered to the relevant data cells and seismic velocity to bemeasured at the field is estimated. Developed system estimates the ripper outputs of the dozers by usingripper production charts, cost and duration of the earthwork task is computed and likelihoods of the feasibilityof the construction machines are estimated. Developed system takes the construction duration into accountand solves time-cost trade-off problem for the selection of the best construction machine. Developedmethodology is implemented on the excavation of the foundations of a mass public housing project with 72houses. Utilization of ripper production charts without performing seismic velocity tests become possible bythe proposed method. Furthermore, time cost trade-off problem is formed and solved without humaninterruption. The developed decision support system proposes the construction machine with least total directand indirect costs. Contractors would be able to reduce their construction costs and gain competitiveadvantage on their rivals, if they implement the proposed system.
Anahtar Kelime:

Belge Türü: Makale Makale Türü: Araştırma Makalesi Erişim Türü: Erişime Açık
  • [1] Kartam N, Flood I (2000) Construction simulation using paralel computing environments. Automation in Construction, 10:69–78.
  • [2] Shi J, Abourizk S (1998) Continuous and combined evenprocess models for simulating pipeline construction. Construction Management and Economics, 16:489–498.
  • [3] Tserng HP, Ran B. Russell J S (2000) Interactive path planning for multi-equipment landfill operations. Automation in Construction, 10:155- 168.
  • [4] Shi JJ, Zeng SX, Tam CM. Modelling and simulation of public housing construction in Hong Hong. 1998 Winter Simulation Conference, 13-16 Dec. 1998, Washington, DC, USA.
  • [5] Sağlam B, Bettemir ÖH (2018) Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. Journal of Construction Engineering, Management and Innovation, 1(2): 85-94.
  • [6] Bettemir ÖH (2018) Development of spreadsheet based quantity take-off and cost estimation application. Journal of Construction Engineering, Management and Innovation, 1(3):108-117.
  • [7] Munshaw V, Trivedi J (2016) Selection of tower cranes through Artificial Neural Network model. Journal of Image Processing & Pattern Recognition Progress, 3(2):67-79.
  • [8] Trivedi JS, Kumar R (2013) Optimization of construction equipment utility using Neural Networks. NICMAR: Journal of Construction Management, 28(3):43-50.
  • [9] Rausch P (2010) Intelligent performance and cost analysis of construction machines’ data. Journal of Intelligent Computing, 1(1):13-19.
  • [10] Lim HC, Lee HC, Lee DE. Economic excavator configuration for earthwork scheduling. International Conference on Architecture and Civil Engineering, January 2018, London, UK.
  • [11] Karshenas S, Farid F (1987) Multiloader-truck fleet selection for earth moving. Transportation Research Record, 1186:51-65.
  • [12] Karshenas S (1989) Truck capacity selection for earthmoving. Journal of Construction Engineering and Management, 115(2):212-227.
  • [13] Chan CMR, Harris FC (1989) A database/spreadsheet application for equipment selection. Construction Management and Economics, 7(3):235-247.
  • [14] Unit Price Book, Republic of Turkey Ministry of Environment and Urbanization, Directorate of Higher Technical Board, Construction and Installation Unit Prices.
  • [15] Caterpillar Inc. (1997). Caterpillar performance handbook. Caterpillar.
  • [16] Nunnally SW. Construction Methods and Management. 6th edition, McGraw-Hill, USA, 2003.
  • [17] Peurifoy RL, Schexnayder CJ. Construction Planning, Equipment and Method, 6th edition, McGraw-Hill, USA, 2002.
  • [18] Sharma PK, Singh TN (2008) A correlation between P-wave velocity, impact strength index, slake durability index and uniaxial compressive strength. Bulletin of Engineering Geology and the Environment, 67(1):17-22.
  • [19] Zukui L, Xinxu Z, Jinhai Z, Daixu T, Yongsong T, Jing Y, Yanqing L (2001) The experiment investigation of the correlation of acoustic logging and rock mechanical and engineering characteristics. In: Wang S, Fu B, Li Z. (ed) Frontiers of Rock Mechanics and Sustainable Development in the 21st Century, CRC Press, 2001, pp. 89-92.
  • [20] Babacan AE, Ersoy H, Gelişli K (2012) Kayaçların fiziksel, mekanik ve elastik özelliklerinin ultrasonik hız tekniği ve zaman-frekans analiziyle belirlenmesi: bej kireçtaşları (KD Türkiye) üzerine örnek bir çalışma. Jeoloji Mühendisliği Dergisi, 36(1):63-73.
  • [21] Goktan RM. Theoretical and practical analysis of rock rippability. Ph.D. Thesis, Istanbul Technical University, 1988.
  • [22] Christaras B, Mariolakos I, Foundoulis J, Athanasias S, Dimitriou A. Geotechnical input for the protection of some Macedonian Tombs in Northern Greece. 4th International Symposium Conservation of Monuments in The Mediterranean Basin, 6-11 May 1997, Rhodes, Greece, pp. 125- 132.
  • [23] Altindag R (2012) Correlation between P-wave velocity and some mechanical properties for sedimentary rocks. Journal of the Southern African Institute of Mining and Metallurgy, 112(3):229- 237
  • [24] Yagiz S (2011) P-wave velocity test for assessment of geotechnical properties of some rock materials. Bulletin of Materials Science, 34(4):947.
  • [25] Mendenhall WM, Sincich TL. Statistics for Engineering and the Sciences. Chapman and Hall/CRC, 2016.
  • [26] Morris J. Geology Book, The. New Leaf Publishing Group, 2000.
APA Bettemir Ö, ÖZDEMİR E, Eren Sarıcı d (2021). Selection of construction machine by considering time-cost trade-offproblem. , 173 - 186. 10.31462/jcemi.2021.03173186
Chicago Bettemir Önder Halis,ÖZDEMİR Engin,Eren Sarıcı didem Selection of construction machine by considering time-cost trade-offproblem. (2021): 173 - 186. 10.31462/jcemi.2021.03173186
MLA Bettemir Önder Halis,ÖZDEMİR Engin,Eren Sarıcı didem Selection of construction machine by considering time-cost trade-offproblem. , 2021, ss.173 - 186. 10.31462/jcemi.2021.03173186
AMA Bettemir Ö,ÖZDEMİR E,Eren Sarıcı d Selection of construction machine by considering time-cost trade-offproblem. . 2021; 173 - 186. 10.31462/jcemi.2021.03173186
Vancouver Bettemir Ö,ÖZDEMİR E,Eren Sarıcı d Selection of construction machine by considering time-cost trade-offproblem. . 2021; 173 - 186. 10.31462/jcemi.2021.03173186
IEEE Bettemir Ö,ÖZDEMİR E,Eren Sarıcı d "Selection of construction machine by considering time-cost trade-offproblem." , ss.173 - 186, 2021. 10.31462/jcemi.2021.03173186
ISNAD Bettemir, Önder Halis vd. "Selection of construction machine by considering time-cost trade-offproblem". (2021), 173-186. https://doi.org/10.31462/jcemi.2021.03173186
APA Bettemir Ö, ÖZDEMİR E, Eren Sarıcı d (2021). Selection of construction machine by considering time-cost trade-offproblem. Journal of Construction Engineering, Management & Innovation (Online), 4(3), 173 - 186. 10.31462/jcemi.2021.03173186
Chicago Bettemir Önder Halis,ÖZDEMİR Engin,Eren Sarıcı didem Selection of construction machine by considering time-cost trade-offproblem. Journal of Construction Engineering, Management & Innovation (Online) 4, no.3 (2021): 173 - 186. 10.31462/jcemi.2021.03173186
MLA Bettemir Önder Halis,ÖZDEMİR Engin,Eren Sarıcı didem Selection of construction machine by considering time-cost trade-offproblem. Journal of Construction Engineering, Management & Innovation (Online), vol.4, no.3, 2021, ss.173 - 186. 10.31462/jcemi.2021.03173186
AMA Bettemir Ö,ÖZDEMİR E,Eren Sarıcı d Selection of construction machine by considering time-cost trade-offproblem. Journal of Construction Engineering, Management & Innovation (Online). 2021; 4(3): 173 - 186. 10.31462/jcemi.2021.03173186
Vancouver Bettemir Ö,ÖZDEMİR E,Eren Sarıcı d Selection of construction machine by considering time-cost trade-offproblem. Journal of Construction Engineering, Management & Innovation (Online). 2021; 4(3): 173 - 186. 10.31462/jcemi.2021.03173186
IEEE Bettemir Ö,ÖZDEMİR E,Eren Sarıcı d "Selection of construction machine by considering time-cost trade-offproblem." Journal of Construction Engineering, Management & Innovation (Online), 4, ss.173 - 186, 2021. 10.31462/jcemi.2021.03173186
ISNAD Bettemir, Önder Halis vd. "Selection of construction machine by considering time-cost trade-offproblem". Journal of Construction Engineering, Management & Innovation (Online) 4/3 (2021), 173-186. https://doi.org/10.31462/jcemi.2021.03173186